Competitive Tenders

Description

Where a procurement requirement has been identified and the strategy to procure the requirement is to be "competitively tendered", then you should follow this process guidance. This should be read in conjunction with Step 4, 5 and 6a documents.

External spend is subject to the following competition thresholds:

When you must obtain quotations/tenders

Note: Major competitive tenders (>£100k) to be issued via In-Tend (e-tender platform)

Value From (exc. VAT) Value To (exc. VAT): Tendering Requirements:
£0 £10,000

Order may be made without competitive quotations

£10,000 £20,000 Seek at least 3 written quotations - obtaining at least 2
£20,000 £50,000

Seek a minimum of 3 written quotations or tenders

The decision and reasons must be entered in the contract file

£50,000 £100,000 A minimum of 3 tenders must be invited
>£100,000   Consult with Procurement who will carry out the tender

Engagement

  • End User Client to establish requirements to procure
  • Category Manager (Abad Zalal - a.zalal@imperial.ac.uk) to advise and support on tendering matters and lead on major competitive tenders
  • Responsible Director of Department to support the competitive tender process 
  • Project Team to support delivery of the competitive process (where applicable)
  • Space & Building Information Team to support the tender process in terms of BIM and Records requirements
  • Sustainability Programme Manager to support the implementation of the sustainability criteria into tenders 

Forms & Links

Approvals & Compliance Review

Category Manager will review and approve all competitive tender packs. 

Repeated Subsequent RIBA Stages 

Competitive tenders can occur at multiple RIBA stages depending on the requirement.