Decant Strategy
Description
Prior to an area being handed over to the contractor for works existing items, including but not limited to: furniture, ICT equipment and laboratory equipment need to be removed from the area.
Engagement
- End-users of the existing space, this can be via the User Coordinator for the project.
- ICT and/or AV Team
- Property Service Operations
- External furniture removers (if required)
- Appointed Contractor
Forms & Links
Equipment Decontamination Form: CSM20 Equipment Decontamination
Area Clearance Decontamination Form: CSM21 Area Clearance Decontamination Certificate
Repeated Subsequent RIBA Stages
RIBA Stage 1
Complete a furniture/equipment inventory. Allow a budget cost for decant within the cost plan.
RIBA Stage 4
Confirm the following:
- What furniture/equipment needs to be moved out of the area for the start of the project.
- Who will be moving the following: department, property services team, external furniture remover, appointed contractor. This may be a mix of all four and will vary with each project.
- Can any of this furniture/equipment be used elsewhere.
- When furniture/equipment needs to be moved by.
- Produce and issue a Decant Strategy Programme and schedule in various moves.
- Arrange for area and equipment decontamination as and when required by the User Coordinator.
RIBA Stage 5
As and when required, issue signed CSM20 and CSM21 to contractor.