Activity | Date |
---|---|
Procurement – Tender process - complete | January - May 2023 |
Discovery & Consultation - complete | June to October 2023 |
Requirements gathering (staff and students) - complete | June/July 2023 |
Design Phase (aligned with Imperial brand project) - complete | November 2023 to April 2024 |
Implementation phase | March to August 2024 |
Priority content population |
July to October 2024 |
Launch of new website | September 2024 |
Training provided for new content types |
October 2024 |
Support and content strategy implementation | November 2024 to March 2025 |