New Wi-Fi is being rolled out in a phased approach across Imperial's campuses and halls of residence from June 2024. The full rollout is expected to take 18 months.

This page will continue to be updated throughout the rollout with any changes made and completed works.

Timeline of Wi-Fi works

Silwood Park Campus

  • All teaching spaces and most halls of residence

South Kensington Campus

  • ACE Extension Building
  • Abdus Salam Library
  • Blackett Laboratory
  • Bone Building
  • Business School
  • Chemistry Building
  • City and Guilds Building
  • Dyson School of Design Engineering
  • Electrical and Electronic Engineering Building
  • Faculty Building
  • Flowers
  • Huxley Building
  • RCS1
  • Roderic Hill Building
  • Royal School of Mines
  • Sherfield Building
  • Sir Alexander Fleming Building
  • Sir Ernst Chain Building - Wolfson Laboratories
  • Skempton Building
  • William Penny Laboratory

White City Campus

  • 88 Wood Lane
  • Gate House
  • I-Hub (Levels 5 and 6)
  • Molecular Sciences Research Hub
  • Scale Space
  • School of Public Health
  • Sir Michael Uren Building
  • Stadium House

South Kensington Campus

August
  • 14-15 Princes Gardens
  • 170 Queen's Gate
  • 52-53 and 55 Princes Gate
  • Bessemer Building
  • Early Education Centre
  • Ethos Sports Centre
  • Garden Cottage
  • Weeks Hall

Putney Boat House

October-December 2024

  • Hammersmith Campus
  • Chelsea & Westminster Campus
  • Royal Brompton Campus
  • North West London Hospitals (Hillingdon)
  • Harlington Sports Ground

January - October 2025

  • St Mary's Campus
  • West Middlesex Hospital
  • North West London Hospitals (Northwick Park)
  • Harefield Hospital
  • North Acton Halls of Residence
  • Silwood Park Halls of Residence